A new intermodal transit hub connecting commuter rail, bus rapid transit, and a future light-rail line beneath a sweeping ETFE roof structure.
Rail operations could not be interrupted. The team executed seventeen single-night possessions to set primary steel directly above the live tracks.
Tension cable system was modeled and stress-tested off-site, allowing on-site assembly to proceed in four weeks rather than the eleven originally projected.