Central Line Transit Hub
Infrastructure · Detroit, MI · 2023

Central Line Transit Hub

Size
168,000 sq ft
Duration
30 months
Delivery
Construction Manager at Risk
Client
Regional Transit Authority
Overview

A new intermodal transit hub connecting commuter rail, bus rapid transit, and a future light-rail line beneath a sweeping ETFE roof structure.

Scope of work
01
  • ·Steel-and-cable tension roof structure
  • ·Below-grade platforms and concourse
  • ·Public art integration and wayfinding
  • ·Adjacent street and streetscape reconstruction
Challenges & solutions
02

Rail operations could not be interrupted. The team executed seventeen single-night possessions to set primary steel directly above the live tracks.

Construction process
03

Tension cable system was modeled and stress-tested off-site, allowing on-site assembly to proceed in four weeks rather than the eleven originally projected.

Gallery — Central Line Transit Hub
Central Line Transit Hub — Infrastructure project in Detroit, MI